Study Structure and Timing

The economic assessment is structured around 6 work packages:

WP1: Inception phase and assessment of lessons learned from similar studies conducted in East Africa, including a regional meeting organized in Kampala. (January - April 2014).

WP2: Downscaling of climate change scenarios over Uganda, including a capacity building workshop. (January - July 2014).

WP3: Economic modelling at national, sectoral and district levels. (5 case studies + a specific assessment on Kampala urban area) (April 2014 – June 2015).

WP4: Recommendations for policy development and implementation, and priority investments. (April 2014 – November2015).

WP5: Communications & Outreach. (January 2014 – December 2015).

WP6: Management & Q.A. (January 2014 –December 2015).